Arizona · power, water & your bill

No blank checks.
Make them pay their own way.

Arizonans are right to be concerned about large computing projects raising utility bills, straining the grid and using scarce water. This site measures every major project in the state against four enforceable conditions, and uses public records to show where the rules already protect families and where they don't yet.

Who pays for new grid capacity?
100%of the transmission and substations a large-load customer needs are paid by that customer on SRP's system
U.S. homes
+7.4%
Arizona homes
+1.0%

Change in the average residential electricity price, January–June 2026 vs. 2025. A correlation, not proof of cause.

The standard

Four conditions. Every project measured against them.

Not voluntary pledges. Each condition is graded on what is written into law, utility tariffs or binding agreements today.

01

Pay for the power they use

Partly in place
  • SRP requires new large loads to pay up front for the transmission and substations built to serve them
  • APS has proposed a 45%+ rate increase for its extra-high-load customer class, versus about 14% for homes
  • No statewide rule yet requires every utility to do the same
02

Protect families from higher bills

Being tested
  • SRP bills customers over 20 MW for at least 80% of their forecast demand, whether they use it or not
  • Commission staff found Project Blue's power contract shifts no costs to homes; the Attorney General's appeal is pending
  • A 2026 law requires utilities to report large-load requests and cost-allocation studies
03

Protect local water

Gaps remain
  • Goodyear requires air cooling on Microsoft's newest buildings
  • Phoenix, Tempe, Mesa and others cap or review large-volume water users
  • Arizona has no statewide water-use reporting requirement for data centers; the Governor's proposed water-use fee was not enacted
04

Enforceable accountability

Partly in place
  • New sales-tax exemptions are paused from July 2026 to June 2029
  • Certified facilities that miss their investment commitments can lose the tax relief
  • Arizona's exemption carries no job or wage requirements, unlike Nevada's and Texas's
What it means for Arizona

When they pay their own way, the public comes out ahead

Estimated yearly state and local tax revenue from projects operating or under construction today, set against what the state gives up. Adjust every assumption in the public ledger.

Why the numbers differ

Trackers disagree. Here's why, and which number we use.

Same buildings, different question

Explore

Look it up yourself